| This
10 gate, 270,000 square foot terminal designed by WNB+A for
Delta Airlines was the first new terminal built at LaGuardia
Airport in over 10 years. The concept of this project was to
create a terminal that would be operational efficient with a
modern image. This terminal was the first fast-track project
built at a Port Authority of New York & New Jersey facility.
WNB+A worked together with the Port Authority NY & NJ to develop
"fast-track" review policies and procedures. WNB+A functioned
as A/E team prime, and sole architects, |
|
 |
 |
 |
| |
 |
 |
 |
 |
|
|
|
 |
 |
|
 |
|
 |
 |
 |
 |
 |
| |
 |
| The
purpose of this $200 Million project was to provide an enlarged,
upgraded terminal to serve both British Airways and United Airlines
in a joint operation. To meet this goal, a new 100,000 s.f.
addition was added to the existing terminal. A prime consideration
in this complex project was to maintain operations throughout
construction. In order to provide uninterrupted service, the
construction was completed in 17 phases. WNB+A functioned as
A/E team prime, sole architects, and program managers for this
important project. It finished on time and under budget. |
|
 |
 |
 |
| |
 |
 |
 |
 |
|